The Indonesian Guotai electric power plant project is located in the south of Indonesia Province, about 60 km south of the city of Musa, south of Sulawesi province. The construction period of the 2 100 megawatts circulating fluidized bed curing unit is 30+3 months. The owner is Indonesian national power company (PLN). The project is a preferential buyer's loan project for the Chinese government. It is contracted by the China energy construction group, Anhui Power Construction First Engineering Co., Ltd. EPC.
The main works of the project include the construction of the main building, steam turbine foundation, boiler and boiler elevator shaft foundation, first (once) fan room or hanger foundation, post furnace floor, dust collector foundation and small room, flue support foundation, draft fan bracket and fan foundation, limestone powder warehouse, slag warehouse Foundation, steel ash warehouse foundation, air compressor room and ash control building, gasification fan room, turbine house A excluded structures, diesel generator room, diesel boiler room, start-up boiler room, unit drainage tank and water pump building and building small installation (electrical lighting, ventilation air conditioning, fire fighting, water supply and drainage) project, etc., the project was completed in March 2018. Fudong construction as participation